Gazprom Pererabotka Blagoveshchensk (investor, owner and operator of the Amur GPP) funds were used to purchase the following items: a mobile digital laboratory, chemical reagents, chemical utensils, stand rods, Petri dishes, an electronic showcase demonstrating solubility of acids, bases and salts in water, Mendeleev's periodic system of chemical elements, and much more.

16 final-year students of the Amur Technical College in Svobodny have completed their on-the-job training at the Amur Gas Processing Plant.

Teachers and postgraduates majoring in cryogenic gas mixtures separation process got acquainted with the features of the process at one of the most modern and high-tech gas processing plants.

Gazprom Pererabotka Blagoveshchensk (the investor, the owner and the operator of the Amur GPP) has purchased the following equipment for the handicraft lessons: sewing machines, an overlock sewing machine, a steam generator, specialized furniture as well as tables, racks and shelves, equipment for making badges, a computer, and a printer.

The career guidance meetings were held at the following educational institutions: Tomsk Industrial and Humanitarian College, National Research Tomsk State University, Tomsk Polytechnic College, Tomsk State University of Control Systems and Radioelectronics.

64 application forms have been accepted from the students wishing to have on-the-job training with subsequent employment at the Amur GPP.

16 students of the Amur Technical College in Svobodny are having their on-the-job training at the Amur Gas Processing Plant. All of them are going to complete training in the following professions this year: environmental laboratory assistant, technological pump and compressor operator, oil refinery operator.

Restoration and pre-commissioning are in progress at process lines 1 and 2. Pre-commissioning and commissioning are continuing, construction and installation of the process pipelines are complete, and handover of the heating tracing systems into operation is nearing completion at process line 3.

Construction of a multifunctional sports centre at the Amur GPP administrative area has been completed.

Internal purging followed by nitriding and connection of pipelines have been completed on eight spherical tanks of this farm. Commissioning is in progress.