News

January 2022 year

Eight units simulating the processes in a real production environment were purchased and installed under the guidance and with financial assistance from Gazprom Pererabotka Blagoveshchensk LLC.

Yuri Lebedev, General Director of Gazprom Pererabotka Blagoveshchensk LLC and Andrey Plutenko, rector of Amur State University.

This information was presented by Aleksandr Grebenyuk, Doctor of Medical Sciences, Professor, Head of Medical Safety of NIPIGAS JSC at the request of Amur GPP/Amur GCC Public Council.

This unit is intended to separate the liquid phase from the ethane fraction stream. Deethanizer column is part of the complex licensed low-temperature natural gas separation units.

Commissioning personnel is now performing oil flushing of the lubrication system of the gas turbine units and the centrifugal compressor, individual tests and functional tests of individual components. Shaft alignment and other activities are also being carried out.

Seven-storey building with a total area of almost 7,000 square meters is 92% complete. Finishing works are nearing completion now.