During the last month, they’ve been working on the first train of the plant and in central laboratory. Students have studied the low-temperature processes and operation of cryogenic equipment for liquefaction and extraction of helium, methane and other hydrocarbon gases.

The experts of the Far Eastern Center of Laboratory Analysis and Technical Measurements have completed the planned research of environmental conditions at the Amur GPP construction site. The results of comprehensive industrial environmental monitoring have proven the compliance of main parameters with Russian and international environmental safety standards.

These are the largest pieces of equipment to be delivered to the Amur GPP during the summer navigation of 2021. Demethanizer weight is 870 tons, the length is 88 m. Nitrogen rejection unit with a length of over 58 meters weighs 883 tons.

Investor and owner of construction of the Amur Gas Processing Plant allocated over three million rubles for this purpose under an agreement with the district administration. Old wooden window frames were replaced with metal and plastic ones in Chernigovka school. Not only the windows, but also the entrance doors were replaced at the Yukhta school.

The second train of Amur GPP is under preparation for hot commissioning. The second pair of Ladoga gas pumping units of the booster compressor station is ready for cold start.

During this month, they are going to be trained on the plant first train and central laboratory.

14 chemistry students have successfully defended their degree theses, prepared with taking into consideration the needs of the leading enterprises of the chemical industry, and first and foremost — the needs of Amur Gas Processing Plant. Seven of the graduates are going to build their careers on Amur Gas Processing Plant.