Central laboratory has been put into operation at the Amur Gas Processing Plant
Its staff will evaluate the parameters of the feed gas, control the quality of the products and conduct intermediate control of the process.
The last bell rang for the eleventh-graders of Gazprom class of school No. 1 in Svobodny
Heads of Gazprom Pererabotka Blagoveshchensk came to congratulate the 26 students. Five of the most active students were awarded certificates for 5,000 rubles.
Training of the operational staff of the plant has begun in the new training and production center of the Amur Gas Processing Plant
With the participation of the representatives of the developers of the process equipment, specialists in the field of gas processing work out their practical skills of starting up the Amur GPP units at the on computer training complexes.
Regular environmental monitoring campaign took place in the construction area of the Amur Gas Processing Plant
Experts of the Federal State Budgetary Institution «Center for Laboratory Analysis and Technical Measurements in the Far Eastern Federal District» took samples of atmospheric air, surface water, bottom sediments and soil, and measured the noise level.
Mechanical availability of the main gas separation unit of the first process line of the Amur Gas Processing Plant has been achieved
Hundreds of professionals of the project owner Gazprom Pererabotka Blagoveshchensk, general contractor NIPIGAS, supplier of the equipment of the partner companies are currently involved in commissioning.
Commercial metering stations for feed and commercial gas of the Amur Gas Processing Plant ready for operation
Tests are carried out on the measuring equipment designed for continuous monitoring of the volume, pressure, temperature, density, and composition of the gas.
Mass vaccination against COVID-19 begins at the construction site of the Amur Gas Processing Plant
In total, 20 thousand doses of Sputnik V vaccine will be used during the vaccination campaign. Four thousand doses have already been received, with 12 thousand doses more to be delivered in the near future
Overall progress of the Amur Gas Processing Plant construction project in April 2021 was 75.1%
Commissioning is in progress at start-up complex 1. The site is connected to Power of Siberia main gas pipeline. All four tie-ins of the commercial and feed gas pipelines have been completed.