News
March 2021 year
Trial run of the air compressor took place at the nitrogen and air unit
The work was carried out under commissioning operations at the Amur Gas Processing Plant.
Students of the Amur State University are mastering specialization program at Gubkin Russian State University of Oil and Gas with the support of Gazprom Pererabotka Blagoveshchensk LLC
In a month, the students will return to Amur State University to prepare their final qualification papers. Before the presentation, six company-sponsored students will undergo practical training at the Amur Gas Processing Plant, and will also continue their master's degree programs.
Yuri Trutnev about the Amur Gas Processing Plant: «A huge amount of investment, a huge and well-coordinated work of people; it only commands respect that they move without disrupting the schedule.»
Deputy Prime Minister of the Russian Federation — Plenipotentiary Representative of the President of the Russian Federation in the Far Eastern Federal District visited the plant under construction today. Yuri Lebedev, General Director of Gazprom Pererabotka Blagoveshchensk, told him about the implementation of the project.
The building of the service and operational unit for the power supply services is welcoming the employees at the construction site of the Amur Gas Processing Plant.
It is designed for simultaneous work of 286 professionals, and the total area of the five-storey building is about 8,000 square meters.
Commissioning at the cryogenic gas separation unit of the first process line of the Amur Gas Processing Plant
Loop tests of compressors and expanders are in progress. At the moment, the professionals are conducting additional tightness tests on the process pipelines, as well as functional tests of the emergency shutdown system.
Letter of gratitude from the Svobodny Hospital was presented to the staff of Gazprom Pererabotka Blagoveshchensk
In February 2021, the overall construction progress of the Amur Gas Processing Plant reached 72.8%
The installation of process pipelines has been completed on the Licenced Units of Start-up Complex 1 (1st and 2nd process lines), and work is in progress to insulate and install its electric heat systems. Commissioning works at the Compressor station are under completion.