Amur GPP construction reaches 91.31% completion in early April 2024

Three of its process lines generate commercial gas products. Helium treatment, liquefaction and loading unit 1 and 2 operate in their normal process mode. High-purity liquefied helium (99,9999%) is shipped on a regular basis. Watch our video for details about the progress on process lines 4, 5, and 6.