Installation of the feed gas cooling unit is complete on Amur GPP process line 5

The last module of the cold box was installed on the Amur GPP process line 5. This equipment is an important element of the complex of cryogenic technological equipment and is intended for cooling the natural gas entering the plant before being fed to the gas separation columns.


The feed gas cooling unit consists of seven modules which are all different sizes, weighing from 70 to 280 tons. Total weight of the installed equipment of the cold box is about 1,400 tons, its height is more than 77 meters. A heavy-duty concrete base has been prepared for assembling the unit. The modules are assembled into a single unit using a crane with a lifting capacity of 1,600 tons.