November 2021 year
Mechanical repair workshop at Amur GPP in preparation for installation of inter-shop equipment
It is planned to install more than four hundred pieces of equipment, in particular, vertical milling, turning, screw-cutting, gear spline milling, drilling and grinding machines, plasma cutting machines, and argon arc welding system will be placed there.
160 thousand tons, or more than three quarters of all steel structures, have already been installed at the Amur Gas Processing Plant
These include process pipeline racks, frames for the gas separation equipment, flight ladders, and other elements of the plant production facilities. This amount of steel is enough to build two dozen Eiffel Towers.
Kazan scientists to take part in development of advanced training programs for Amur GPP operational staff
Representatives of Kazan National Research Technological University management visited the Amur GPP site. The purpose of the meeting was the development of additional programs for advanced training and professional retraining of the staff of the new plant.
Tenth-graders of Gazprom сlass in Svobodny take part in 2021 All-Russian Eco-Dictation
Gazprom class students took part in the All-Russian Eco-Dictation 2021. It was held at Svobodny school 1 which became the official venue of the event.
Overall progress of Amur GPP construction in October 2021 amounted to 81.51%
Overall progress of Amur GPP construction in October 2021 amounted to 81.51%.
Four storage tanks for liquefied helium at the third commerical helium production line of the fifth process train installed at the Amur Gas Processing Plant
Each take has a volume of about 120 cubic meters and is able to hold about 13,000 kg of commercial product.
60% of all pipelines at the main gas separation unit of process line 3 of the Amur Gas Processing Plant have been tested
Possible defects in the pipeline materials and welded joints are identified this way during construction in order to ensure reliable operation of the unit under design conditions.