The first event was held on October 13 at the Bauman Moscow State Technical University and the second one a day later at the Gubkin University. Hundreds of students received consultations on potential employment and on-the-job training and 70 of them filled out the company's questionnaires during this event.

A committee which included the dedicated Gazprom Group employees has issued an affirmative statement and noted the high level of the Amur GPP readiness for winter.

This unit removes moisture, methanol, and other impurities from the feed gas supplied to the plant for further low-temperature gas separation into fractions.

Gor Minasyan, Chief Specialist of the Department for Operation of Buildings and Structures at Gazprom Pererabotka Blagoveshchensk LLC and member of Gazovik team, became the best forward with 13 goals.

The forum aims to establish peer-to-peer links between young professionals in the industry, pool knowledge, create conditions for synergy of skills and competencies of young professionals, develop new solutions and approaches for successful implementation of strategic projects and improve work efficiency.

The experts note already at the sampling stage that the preliminary results of the measurements do not show any deviations from the standards. The final results of the survey will be ready by mid-November.

Restoration and pre-commissioning are underway on the licensed units of the Amur GPP process line 1 and 2. Installation of process pipelines on the gas fractionation unit and the natural gas liquid purification unit of process line 1 has been completed; testing of these process pipelines for strength, blowdown, re-assembly and handover for pre-commissioning are underway.

Gazprom Pererabotka Blagoveshchensk (the investor, owner and operator of the Amur GPP) continues to provide charity to the Svobodny correctional boarding school. Assembly hall of the school is now equipped with a wide-screen TV, a projector and a modern laptop with the company's funds.

In particular, all welding works have already been completed, laying of cable lines, blowdown and re-assembly of the process pipelines are underway.