Pre-commissioning underway on Amur GPP process line 4

Pre-commissioning is underway, construction and installation works are nearing completion on process line 4 of the Amur GPP. In particular, all welding works have already been completed, laying of cable lines, blowdown and re-assembly of the process pipelines are underway.

Loop testing and re-assembly of static equipment are underway, hot running-in of the air cooler motors has been completed, individual and aerodynamic tests of heating, ventilation and air conditioning systems are underway as part of pre-commissioning.

Amur GPP will become one of the world's largest natural gas processing sites with a capacity of 42 billion cubic meters of gas per year. Commercial products, in addition to purified methane, will include ethane, propane, butane, pentane and hexane fraction, and helium. Gazprom Pererabotka Blagoveshchensk LLC (member of Gazprom Group) is the investor, owner and operator of Amur GPP. Construction is managed by JSC NIPIGAS.