Overall progress of Amur GPP construction reaches 84.44% by early April 2022
Restoration and pre-commissioning are in progress at process lines 1 and 2.
Pre-commissioning and commissioning are continuing, construction and installation of the process pipelines are complete, and handover of the heating tracing systems into operation is nearing completion at process line 3.
Installation of the process pipelines, their testing and purging are in an active phase at process line 4.
Equipment is being installed at process line 5, in particular, installation of a buffer tank is complete, and installation of the steel structures for cables has commenced.
Reinforcement of the beams of the rack for installation of oversize equipment, installation of steel structures of the racks for the compressor building, and concreting of walls are in process at process line 6.
Non-licensed units are preparing for a cold start of Ladoga 5 and Ladoga 6 gas pumping units and installation of Ladoga 9–10 units onto their respective foundations.
Finishing works of the premises and installation of machines are in progress in the mechanical repair shop.
The website of Gazprom Pererabotka Blagoveshchensk LLC uses cookies. By continuing to use this site, you agree to allow us to use cookies in your browser with a view to improving user experience. If desired, you may disable the storage of cookies in your browser settings.
The processing of user data is carried out in compliance with the