The overall progress for the Amur GPP construction project in June 2021 is 77.8%
Second process line of the Amur Gas Processing Plant was preparing for hot commissioning in June 2021. The second pair of Ladoga gas pumping units of the booster compressor station is ready for cold start.
Foundation for installation of heavy-lift equipment at the fifth train is completed. The 1600 t capacity ring crane for installation of gas separation columns is installed. Structures of buildings and pipe racks are under installation. As for the third heilum fine purification unit, the structure for main equipment and helium filling tanks is under installation.
The raw gas furnace of the second gas dehydration and purification unit has been fired. 2 process lines (air supply and nitrogen suppy) of the nitrogen and air station are under duty operation.
The central operator room finishing works and landscaping of the adjacent area are completed.
Tank farm No. 3 is fed with NGL in normal mode. Area is under improvement.
Commissioning is underway at the water treatment plant for household and drinking and industrial needs.
The laboratory building has been put into operation.