Amur GPP construction reaches 90.16% completion in early October 2023
Amur GPP process line 1 was put into commercial operation. Commercial products under design specifications were generated, including high-purity liquefied helium (99.9995%).
Loop and functional tests finished on process line 2. The unit for dehydration and removal of impurities is undergoing the commissioning preparations.
Process line 3 switched to its process mode. Commercial products under design specifications were generated. Hot commissioning is in progress at helium treatment, liquefaction and loading unit 2. Electrical works, pre-assembly and tests of pipelines are in progress at the natural gas liquid purification and gas fractionation units.
Watch our video for details about the progress on process lines 4, 5, and 6.
The website of Gazprom Pererabotka Blagoveshchensk LLC uses cookies. By continuing to use this site, you agree to allow us to use cookies in your browser with a view to improving user experience. If desired, you may disable the storage of cookies in your browser settings.
The processing of user data is carried out in compliance with the