Amur GPP construction reaches 89% completion in early June 2023

Process line 1 and 3 of the Amur GPP are seeing the activities to improve the safety systems of the licensed units. Testing of the automated fire alarm, fire fighting and gas contamination detection systems is complete. Installation and commissioning of an ultra-sensitive dynamic laser system for detecting methane leaks are in progress. Installation and commissioning of an advanced process video surveillance system are nearing completion.

Preparations for starting up the heater for drying the lining, as well as individual tests of dynamic equipment are in progress at NGL purification and gas fractionation unit 1.

Revision and maintenance of the process pipelines are nearing completion at line 2. 


Installation of electric heating tracing of pipelines at the licensed units of line 4 as well pre-commissioning are in progress. Pre-commissioning on auxiliary systems is underway at Ladoga gas pumping units 7 and 8. High-voltage tests of transformers and relay protection circuit breakers are completed at the unit for dehydration and removal of impurities (power center). Rostechnadzor's permit for power supply has been obtained.

Line 5 is seeing oil washing of the equipment and commissioning works at the diesel power plants.

A total of 4,297 tons of steel structures have been installed on line 6. Roofing sandwich panels are being installed on the compressor station.