Overall progress of Amur GPP construction by early March is 83.84%
Repair and restoration are underway at start-up complex 1 (process line 1 and 2).
Pre-commissioning and commissioning are in full swing at process line 3. Re-assembly of the process pipelines, insulation of pipelines and equipment of the nitrogen rejection unit are nearing completion. Electric heating systems are being put into operation. Construction and installation in the hangars of Ladoga GPU 5 and 6 are nearing completion.
Process pipelines are being installed at process line 4, and the insulation of the deethanizer and equipment of the nitrogen rejection unit are in progress. Anti-corrosion protection is being applied to the process pipelines. Construction completion of the priority non-process systems like the sewerage, water supply and fire-fighting water supply systems has been achieved.
Concreting of the beam structures is complete on process line 6. Reinforcement of the beams and installation of formwork are underway.
Installation of machines in the mechanical repair shop building has commenced.