Overall progress of Amur GPP construction by early February 2022 amounted to 83.34%
Restoration and pre-commissioning are in progress at process line 1 and 2.
Anti-corrosion coating application on the pipelines is completed; work on their insulation is underway, pre-commissioning and commissioning have entered the active phase. Insulation works on the process pipelines at the helium treatment, liquefaction and loading unit have also reached their end. Ladoga gas pumping units on the same process line 3 are preparing for loop and functional testing.
Installation of pipelines has commenced on process line 5.
Reflux drum, the first licensed unit, is now installed at process line 6; erection of the pipe rack is also underway.
Main construction and installation works are being completed and preparations are underway for commencement of pre-commissioning at the sphere tanks of tank farm 2.
Commissioning is underway at the treatment facilities. Installation of utility lines and electrical works are underway in the maintenance and repair workshop.