Total weight of 26 cargo units is more than 1,200 tons. These include the vessels and parts of the cold box for raw gas for the gas separation unit.

A regular meeting of the Public Council of the Amur GPP and Amur GCC projects was held in Svobodny on August 27. At the beginning of the meeting, it was noted that for the moment the project of the Amur GPP project is around 80%.

Evgeniy Baklanov, Deputy General Director for HR Management of Gazprom Pererabotka Blagoveshchensk LLC, explained the company policy regarding involving local personnel into the Amur GPP.

The tragedy occurred in April of this year. Everything was burned in the fire: furniture, documents, and household appliances. Fortunately, everyone survived. Administration of Svobodnensky district, caring neighbors and friends, as well as Gazprom Pererabotka Blagoveshchensk have come to the rescue.

The installed columns are the key equipment of the gas separation unit which will extract valuable fractions from the multicomponent natural gas received via the Power of Siberia gas pipeline from Chayanda and later Kovykta fields.

By the end of July, the mechanical completion of the main gas separation unit was achieved. Transportation and installation of heavy-lift equipment for the fifth process train was delivered and installed during the 2021 navigation.

Pipeline tests are completed, pipelines have passed the purging procedure. Methane and ethane extraction columns, along with nitrogen removal unit are being prepared for operation.

The equipment is three gas chromatography machines, unique in Russia. These analyzers are purposed for determination of trace contamination in commercial helium, which is important for production of high purity gas at the Amur GPP.

Irina Zakharova, deputy head of the Amur GPP central laboratory.