They will ensure the reception and storage of propane, butane, natural gas liquids (NGL), and pentane and hexane fraction produced at the first start-up complex of the plant.

First meeting of the Public Council of the Amur Gas Processing Plant and Amur Gas Chemical Plant Projects in 2021 was held in Svobodny.

The Chair of the Public Council of Amur GPP and Amur GCC projects Galina Tkachenko

Students will be able to test robots and conduct experiments.

Students of Yukhta rural school

The territory of water sources (spring PMK-11) in Zalineyny microdistrict of the town of Svobodny is a traditional point of spring clean-up for the company employees. This year, the cleaning area was expanded by collecting garbage from the river bank along the road towards the springs.

During the meeting, the supply of process steam to the Amur Gas Processing Plant was started for commissioning purposes. This site will become one of the largest gas processing facilities in the world (42 billion cubic meters per year). The gas will be supplied to the plant via the Power of Siberia gas pipeline.

Svobodnenskaya Thermal Power Plant

A sensory room for psychological relief of the students has been opened in the Svobodny social shelter. Logo Castle equipment and simulators for correcting speech therapy problems in the students was opened in the same room.

Natalia Kosyachun, teacher of the Svobodny social shelter, conducts a lesson

Insulation of the equipment is completed at the gas separation unit of process line 1. Cold box is being filled with perlite. Installation of steel structures on process line 4 continues. A rack is being erected on process line 5 for installation of large-sized equipment in the summer of 2021.

Commissioning operations with the process media with achievement of the design parameters and quality indicators of the process started at the first unit for dehydration and removal of impurities from the feed gas of the Amur Gas Processing Plant. In preparation for this work, the equipment underwent additional tightness and strength tests.

Gazprom Pererabotka Blagoveshchensk professionals participate in commissioning at the first unit for dehydration and removal of impurities from the feed gas

Individual tests of critical utilities, infrastructure, and offsites like the pumps for household, drinking, fire-fighting and industrial water of the onsite pumping station, have been completed.