Working traffic has been opened on the second railway track which connects the construction site of the Amur GPP and the Trans-Siberian Railway. A 460-meter stretch of road is used to deliver an increasing flow of goods to the site.

Specialists of the Center for Laboratory Analysis and Technical Measurements in the Amur Region conducted a study of soil samples in the observation points of the railway infrastructure of the Amur GPP: in the area of the bridge over the Bolshaya Pyora river and two railway stations which equipment is delivered through.

The large-scale drills were organized by Gazprom PJSC, China National Oil and Gas Corporation (CNPC), SOGAZ JSC and Gazprom Pererabotka Blagoveshchensk LLC.

The last batch of equipment for construction of the Amur GPP planned for navigation in 2019 has been delivered to the temporary berth on the Zeya River. In this batch, adsorbers for the fourth process line of the Amur Gas Processing Plant were delivered to the construction site.

A spiral heat exchanger for the third and fourth process lines was installed at the Amur GPP. This is the second heat exchanger manufactured in Saint-Petersburg specially for the Amur Gas Processing Plant.