Cargo delivery plan for navigation 2019 fully implemented

The last batch of equipment for construction of the Amur Gas Processing Plant (GPP) planned for navigation in 2019 has been delivered to the temporary berth on the Zeya River. In this batch, adsorbers for the fourth process line of the Amur Gas Processing Plant were delivered to the construction site.

Navigation in 2019 was the most ambitious for the entire period of implementation of the Amur GPP construction project. From the beginning of June to the beginning of October, 25 barges and tugs with 129 units of large-capacity equipment for the third and fourth lines of the plant were delivered. The total weight of the received equipment is 14.6 thousand tons. The delivery plan is fully implemented, despite the difficulties associated with the flood situation in the region.


Справка

Amur Gas Processing Plant will become one of the world's largest natural gas processing plants. Its design capacity will amount up to 42 billion cubic meters of gas per year. GPP will also include the world's largest production of helium — up to 60 million cubic meters per year.

Amur GPP is an important link in the process chain of natural gas supplies to China in the Eastern route. The plant will receive the multi-component feed gas from Power of Siberia gas pipeline from the Yakutsk and Irkutsk gas production centres currently built by Gazprom with its Eastern Gas Program.

Gazprom Pererabotka Blagoveshchensk LLC (member of Gazprom Group) is the Investor and Owner of Amur Gas Processing Plant project. Construction is managed by NIPIGAS, a leading Russian centre for engineering, procurement, logistics and construction management (member of SIBUR Group). Peak time for construction will be in 2019 to 2020 when over 25,000 workers will be mobilized to the site.