September 2019 year

The weight of the depropanizer is 258 tons, its height is 54.3 m. The weight of the butane column is 134 tons, its height is 48 m.

«Today's release of carp fry into the Zeya river was carried out to support the bioresources in the area of construction of the Amur Gas Processing Plant. In just four years, about 60 thousand young carp have been released into the Zeya river,» said Andrey Belousov, Deputy General Director of Gazprom Pererabotka Blagoveshchensk LLC.

It is designed to cool the natural gas entering the plant before being fed to the gas separation columns and is an important element of the cryogenic gas separation complex.

Industrial environmental monitoring conducted by theFederal State Budgetary Institution “Centre of Laboratory Analysis and Technical Measurement for the Far Eastern Federal District” confirmed that the construction of the Amur GPP is being conducted in full compliance with the Russian and international environmental standards.

The construction personnel of the Amur Gas Processing Plant provided the municipal utility services with equipment with a loading capacity of 100 tons which was used to install an ash collector to the upgraded boiler No. 3 

The second Sports Contest of the employees of the companies participating in construction of the Amur GPP ended today in Svobodny. Athletes competed in a relay race and weight lifting.

The total volume of raw material supplies according to the preliminary agreement is up to 1.5 million tons annually. Prices will be calculated according to the formulas agreed by the parties.

26 tenth graders selected on a competitive basis began their training today in Gazprom class supported by Gazprom Pererabotka Blagoveshchensk LLC. The celebratory assembly dedicated to the Day of Knowledge was held at school No. 1 in Svobodny.