Amur GPP construction reaches 89.18% completion in early July 2023
Process line 1 and 3 of the Amur GPP sees the activities to improve the safety systems of the licensed units complete. Testing of automated fire alarm, fire fighting and gas detection systems is complete; installation and commissioning of ultra-sensitive dynamic laser system for detecting methane leaks are complete; installation and commissioning of an advanced process video surveillance system are complete.
Gas fractionation and NGL purification unit 1 is prepared to receive the product.
Revision and maintenance of the process pipelines are nearing completion at line 2.
Installation of electric heating tracing of pipelines at the licensed units of line 4 as well pre-commissioning are in progress. Cold run of the booster compressor station 4–110V is complete. Fire protection works are underway.
Oil flushing of the equipment is in progress on process line 5.
A total of 4,305 tons of steel structures have been installed on line 6. Installation of the roofing sandwich panels has been completed on the compressor station.
The website of Gazprom Pererabotka Blagoveshchensk LLC uses cookies. By continuing to use this site, you agree to allow us to use cookies in your browser with a view to improving user experience. If desired, you may disable the storage of cookies in your browser settings.
The processing of user data is carried out in compliance with the