Amur GPP construction is 87% complete in early October 2022

Restoration and pre-commissioning are underway on the licensed units of the Amur GPP process line 1 and 2. 

Installation of process pipelines on the gas fractionation unit and the natural gas liquid purification unit of process line 1 has been completed; testing of these process pipelines for strength, blowdown, re-assembly and handover for pre-commissioning are underway.


Application of insulation onto process pipelines and equipment on the helium fine purification, liquefaction and filling unit of process line 3 is nearing completion. Core scope of construction and installation works on the unit for dehydration and removal of impurities has been completed; pre-commissioning is underway.

Pre-commissioning is underway on process line 4: loop testing and re-assembly of static equipment are underway; hot running-in of the air cooler motors has been completed. Welding has been completed, re-assembly and blowdown of the process pipelines and laying of cable lines are underway. Installation and oil flushing are underway at the Ladoga gas compression unit No. 7 and 8. 

Erection of the main steel structures is underway on process line 5. Welding of pipelines and laying of cable lines are underway at the helium fine purification, liquefaction and filling unit.

Erection of the main steel structures and cladding of the compressor room building are underway on process line 6.