Delivery of heavy-lift equipment for Amur Gas Processing Plant in 2021 navigation commences

Delivery of large-capacity and large-size equipment by water during the summer navigation period of 2021 has commenced for the Amur Gas Processing Plant construction project. It is planned to deliver 51 units of equipment for installation of the gas separation units of process line 5 in the coming months. Total weight of the cargo is 5.5 thousand tons, and the volume is almost 35 thousand cubic meters.

Gas separation columns, including the fifth demethanizer, will be delivered to the Amur Gas Processing Plant by sea and river vessels. Modules of the cold box for feed gas designed to lower the temperature of the natural gas entering the plant before being fed to the gas separation columns will also arrive.

The total period of delivery of large-capacity equipment from the sea ports of shipment to the construction site of the Amur Gas Processing Plant will take about three months. Sea vessels will deliver the cargo to the port of De-Kastri (Khabarovsk region) where it will be reloaded onto river barges which-accompanied by tugboats on the Amur and Zeya rivers-will deliver the equipment to the jetty of the Amur Gas Processing Plant in the area of Svobodny town. Unloading will be carried out by two crawler cranes with a lifting capacity of up to 1,350 tons. Next, the equipment will be transported to the construction site along a 27 km long route on self-propelled modular trailers at a speed of 5 km/h.

Background:


The Amur Gas Processing Plant will become one of the world's largest natural gas processing plants with a capacity of 42 billion cubic meters of gas per year. Commercial products will include purified methane, ethane, propane, butane, pentane-hexane fraction, and helium. The first line of the plant was put into operation on June 9, 2021.
Gazprom Pererabotka Blagoveshchensk LLC (member of Gazprom Group) is the investor and owner of the Amur Gas Processing Plant project. Construction is managed by JSC NIPIGAS.