Yuri Lebedev, General Director of Gazprom Pererabotka Blagoveshchensk LLC, informed the Plenipotentiary Representative about the construction.

Participation of construction personnel of the Amur GPP in life of Svobodny and Svobodnensky district was discussed yesterday at the meeting of the Public Council of the company, which was held at the construction site of the plant.

The best students will be eligible for employer-sponsored education by Gazprom Pererabotka Blagoveshchensk LLC and will be sent to the Amur State and Far Eastern Federal Universities, as well as to the key universities of PJSC Gazprom in Moscow, St. Petersburg, Kazan, Tomsk and Irkutsk.

The equipment is installed at the cryogenic units for ethane and NGL extraction, nitrogen rejection and production of nitrogen and helium mixture at the first start-up complex of the Amur Gas Processing Plant.

110 saplings of trees and shrubs were planted on the territory of the sponsored educational institution.

More than 5 thousand piles and about 16 thousand cubic meters of concrete were used to produce the foundations.