Plenipotentiary Representative of the President of the Russian Federation in the Far Eastern Federal District Yuri Trutnev visits the construction site of the Amur Gas Processing Plant
Yuri Lebedev, General Director of Gazprom Pererabotka Blagoveshchensk LLC, informed the Plenipotentiary Representative about the construction.
Amur GPP construction site welcoms the meeting of the Public Council
Participation of construction personnel of the Amur GPP in life of Svobodny and Svobodnensky district was discussed yesterday at the meeting of the Public Council of the company, which was held at the construction site of the plant.
Farewell bell rings for the first Gazprom class under the auspices of Gazprom Pererabotka Blagoveshchensk LLC
The best students will be eligible for employer-sponsored education by Gazprom Pererabotka Blagoveshchensk LLC and will be sent to the Amur State and Far Eastern Federal Universities, as well as to the key universities of PJSC Gazprom in Moscow, St. Petersburg, Kazan, Tomsk and Irkutsk.
Feed gas expanders at the first start-up complex of Amur Gas Processing Plant installed
The equipment is installed at the cryogenic units for ethane and NGL extraction, nitrogen rejection and production of nitrogen and helium mixture at the first start-up complex of the Amur Gas Processing Plant.
Employees of Gazprom Pererabotka Blagoveshchensk LLC launch Let's Green the City Together campaign
110 saplings of trees and shrubs were planted on the territory of the sponsored educational institution.
Foundation works for installation of equipment of third process line of Amur Gas Processing Plant complete
More than 5 thousand piles and about 16 thousand cubic meters of concrete were used to produce the foundations.