Overall progress of Amur GPP construction by early August 2022 amounted to 86%

Restoration and pre-commissioning are underway on process lines 1 and 2.

Pre-commissioning on the major equipment and internal checks of instrumentation in the control room are underway on process line 3. Tests of the foam extinguishing system, sprinkler systems, water discharge of the fire monitor and additional tests of the process pipelines for tightness have been completed at the helium treatment, liquefaction and loading unit. Pre-commissioning on Ladoga gas pumping units No. 5 and No. 6 have been completed.

Individual tests of heating, ventilation and air conditioning systems are underway in the indoor switchgear building and transformer substation on process line 4. The substation is ready to receive power.

Installation of sandwich panels and the major equipment of the control system is underway in the indoor switchgear building on process line 5.

Assembly of the steel and reinforced concrete structures and construction of the driveways and landscaping of the territory are underway on process line 6.
Commissioning of equipment has been completed at the sewage treatment facilities; industrial storm runoff is being processed and treated runoff is being supplied for own needs; processes are being tuned in order to achieve their design performance.