Overall progress of Amur GPP construction by early July 2022 amounted to 85.82%
Restoration and pre-commissioning are underway on the process lines 1 and 2.
Pre-commissioning on the major equipment is underway on the process line 3. Finishing works in the compressor building are nearing completion. Construction and installation works and handover of the systems to commissioning are underway on the unit for dehydration and removal of impurities from the feed gas.
Installation and testing of the process piping and insulation of the equipment are underway on the process line 4.
Cold box modules assembly and installation of the reflux pumps of the gas separation columns and internals are underway on the process line 5. Installation of the main PCS equipment in the indoor switchgears and transformer substation buildings has completed.
Reinforcement of the rack slab is underway on the process line 6. Concreting of the floors and brickwork are nearing completion in the compressor building. Concreting of the walls of the indoor switchgear and transformer substation buildings has completed. Installation of the steel structures, construction of the driveways and landscaping of the territory are ongoing.
The website of Gazprom Pererabotka Blagoveshchensk LLC uses cookies. By continuing to use this site, you agree to allow us to use cookies in your browser with a view to improving user experience. If desired, you may disable the storage of cookies in your browser settings.
The processing of user data is carried out in compliance with the