Process equipment installation started at  Amur GPP 4th process line

Process equipment installation started at 4th process line of Amur gas processing plant (GPP). At present, filters, raw gas adsorbers are installed, designed to purify natural gas to be processed, as well as separators, buffer, drainage, reflux vessels.


Main gas separation columns for Amur GPP 4th process line will be delivered by water transport.

Справка

Amur GPP will become one of the world's largest natural gas processing plants. Its design capacity will be 42 billion cubic meters of gas per year. The plant will consist of six process lines. In addition to the purified methane fraction, the GPP commercial products will include ethane, propane, butane, pentane and hexane fraction, and helium.
Commissioning of the first two lines of the plant, which is currently being arranged, is scheduled for 2021.
Gazprom Pererabotka Blagoveshchensk LLC (member of Gazprom Group) is the Investor and Owner of the Amur Gas Processing Plant project. Construction is managed by NIPIGAS JSC, a leading Russian centre for engineering, procurement, logistics and construction management (part of SIBUR Group).